![]() The first step is to save an interim plan. If you add a couple barstyles to your view you can easily see all changes that were made in an editing session. ![]() It stores the start and finish dates of tasks into the user defined start and finish fields (Start1-Start10 and Finish1-Finish10). An interim plan is really a very simple baseline. That is through the use of an Interim Plan. ![]() But we have no way of knowing from this feature.įortunately Project has had the ability to show the effects of changes in a robust and persistant way. This is a very simple project and all the changes are one for one, but in some cases a major change to one task may change another by only a very small amount.